Construction has ramped up during the summer months, with multiple impacts for commuters across Ottawa. 

Several road closures are planned for the second and third weeks of July, potentially causing longer commutes for residents across the city. Some closures will be ongoing for several months whereas others are for a shorter period of time.

The following is a list of road closures starting this week and next in the Nation’s Capital — as well as upcoming and ongoing closures — based on the City of Ottawa website:

Road closures this week and next

  • Intersection of Barnsdale Road and Rideau Valley Drive: Lane reductions and/or lane shifts are anticipated. Work is planned the week of July 15, and should take two to three days to complete.
  • Hillcrest Avenue from Princeton Avenue to Byron Avenue: The roadway will be resurfaced between July 15 and August 9. Various lane reductions, alternating traffic and/or detours can be expected.
  • Tremblay Road from Avenue U to St Laurent Boulevard: Tremblay Road will remain open to traffic with lane closures expected. Work started on July 15, with completion anticipated by fall 2024.
  • Montcalm Street from Greenfield Avenue to the dead end and Concord Street North from Greenfield Avenue to Havelock Street: Full road closures, local access to Montcalm Street and Concord Street North will be maintained. Montcalm Street and Concord Street will be closed between July 22 and November 29, 2024.
  •  Old Innes Road from Bantree Street to 110m West of Bantree Street: Lane reductions, alternating traffic and/or detours can be expected. This work is scheduled to start July 17, to be complete by fall 2024.

Upcoming road closures

  • Baseline Road from Zena Street to Farlane Boulevard: The road will remain open to traffic with lane closures expected. Work will begin the week of August 5 during evening and overnight hours.

Ongoing road closures

  • Greenfield Avenue and Main Street southbound 417 on ramp to Hawthorne Avenue: Closed in the southbound direction from March 11 until early December.
  • Merivale Road right of way between Kirkwood Avenue and Morisset Avenue on the west side of the road: Merivale Road between Kirkwood Avenue and Mayview Avenue will be reduced to one lane in the southbound direction from early July to late September 2024.
  • Highway 417 Eastbound On-ramp, Parkdale Avenue: Parkdale on-ramp closed from May 13 to August 25.
  • Highway 417 Westbound Off-ramp, Aviation Parkway: All lanes closed from May 24 until November 29. 
  • Highway 417 Westbound On-ramp, Pinecrest Avenue to Greenbank Road: All lanes closed. On-ramp closed until August 2024. 