Line 1 O-Train returns to full service
Posted Apr 5, 2023 10:03:35 AM.
Last Updated Apr 7, 2023 07:45:26 AM.
Full service on the Confederation Line resumed just after 7 p.m. on Thursday evening.
RESOLVED: Full Line 1 service has resumed. Trains are available at all platforms and all stations are open. R1 service will be ending shortly. Thank you for your patience.
— OC Transpo (@OC_Transpo) April 6, 2023
Line 1 was completely shutdown between Tunney’s Pasture and Blair on Wednesday morning, after five trains lost power and became stranded during the freezing rain.
OC Transpo said several steps were completed overnight Thursday to restore service in the west, including manually removing ice build-up, re-energizing the system and inspecting stopped trains and removing them. Crews repeated the same steps in the east to get the trains back up and running.